AI data center sites in Ohio

87 Ohio counties scored on transmission, the interconnection queue, power price and tax. Updated October 18, 2026.

Open a county for its queue requests, substations, plants and data centers.

CountyScorePipelinePower price
631.2 GW10.3¢/kWh
601.8 GW10.3¢/kWh
581.1 GW10.3¢/kWh
561.2 GW10.3¢/kWh
55199 MW10.3¢/kWh
542.5 GW10.3¢/kWh
5416 MW10.3¢/kWh
531.4 GW10.3¢/kWh
53305 MW10.3¢/kWh
52594 MW10.3¢/kWh
52-10.3¢/kWh
501.7 GW10.3¢/kWh
50123 MW10.3¢/kWh
5011 MW10.3¢/kWh
491.1 GW10.3¢/kWh
48-10.3¢/kWh
47848 MW10.3¢/kWh
47292 MW10.3¢/kWh
467.2 GW10.3¢/kWh
46150 MW10.3¢/kWh
451.8 GW10.3¢/kWh
451 GW10.3¢/kWh
45614 MW10.3¢/kWh
45200 MW10.3¢/kWh
4521 MW10.3¢/kWh
45-10.3¢/kWh
44845 MW10.3¢/kWh
44169 MW10.3¢/kWh
43600 MW10.3¢/kWh
43340 MW10.3¢/kWh
4332 MW10.3¢/kWh
421.2 GW10.3¢/kWh
421 GW10.3¢/kWh
42754 MW10.3¢/kWh
41227 MW10.3¢/kWh
40325 MW10.3¢/kWh
3920 MW10.3¢/kWh
3915 MW10.3¢/kWh
382.4 GW10.3¢/kWh
381.2 GW10.3¢/kWh
3879 MW10.3¢/kWh
3820 MW10.3¢/kWh
37900 MW10.3¢/kWh
37287 MW10.3¢/kWh
37200 MW10.3¢/kWh
37-10.3¢/kWh
361.4 GW10.3¢/kWh
36150 MW10.3¢/kWh
36125 MW10.3¢/kWh
36-10.3¢/kWh

Pipeline: active generation and storage requests in the ISO queue, or EIA planned plants where larger (outside the ISOs). Top kV: highest substation voltage. Power price: the state's industrial average. DCs: GPU colocation, mining sites and AI campuses.

What the data shows

The strongest Ohio counties for a large AI load are Franklin County (63), Licking County (60) and Trumbull County (58) on the site score. Ohio sits in PJM; its ISO queues hold 51 GW of active generation and storage requests, 5.6 GW of them with a signed interconnection agreement, and it has 98 substations at 345 kV and up.

Industrial power averaged 10.3¢/kWh (EIA, July 2026 YTD), against 8.2¢/kWh a year earlier, the 37th lowest of the 50 states and DC. Ohio has paused new applications for its data center sales tax exemption. We track 9 AI campuses and 36 GPU-ready colocation facilities here.

Top 6 counties in detail

1. Franklin CountyPJM

Site score 63 of 100

Transmission
22/25
Generation pipeline
11/20
Industrial power price
15/20
Existing and retiring plants
1/15
Sales tax exemption
4/10
Data center activity
10/10
Market
PJM
Queue (active)
1.2 GW
Agreement signed
200 MW
Planned plants (EIA)
400 MW
Top substation
345 kV
Substations 230 kV+
5
Operating plants
15 MW
Retired or retiring
3 MW
Industrial power, OH
10.3¢/kWh
Sales tax exemption
Paused

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Beatty 345 kVPJM AG2-376, in service 2024-11Beatty 345 kV400StorageIn study
Cole Road 345 kVPJM AI2-171, in service 2023-12Cole Road 345 kV310SolarIn study
Pleasant Prairie SolarPJM AE2-214, in service 2026-12Cole 345 kV200SolarAgreement signed
Hayden 345 kVPJM AH1-270, in service 2023-12Hayden 345 kV85SolarIn study
Cole 345 kVPJM AH1-318, in service 2025-12Cole 345 kV60StorageIn study
Cole 345 kVPJM AF1-275, in service 2022-12Cole 345 kV50SolarIn study
Obetz 138 kVPJM AG2-498, in service 2025-12Obetz 138 kV50StorageIn study
Bixby 345 kVPJM AG2-499, in service 2025-12Bixby 345 kV50StorageIn study

Substations, 115 kV and up

  • BIXBY · 10 lines345 kV
  • BEATTY · 10 lines345 kV
  • CORRIDOR · 8 lines345 kV
  • HAYDEN · 7 lines345 kV
  • HAYDEN · 4 lines345 kV
  • Unnamed · 6 lines138 kV
  • EAST BROAD STREET · 5 lines138 kV
  • Unnamed · 4 lines138 kV

Planned, retiring and retired plants

  • Pleasant Prairie Solar Energy LLC · Solar, planned 2026200 MW
  • Flint · Storage, planned 2027200 MW

Data centers, AI campuses and mining sites

  • Google Columbus (South High Street) · AI campus, operating · AP via ABC News
  • Cologix COL4 · GPU colocation, Columbus, 50 MW
  • Cologix COL3 · GPU colocation, Columbus, 20 MW
  • Expedient Dublin · GPU colocation, Dublin, 4.8 MW
  • 5C Data Centers CMH01 · GPU colocation, Columbus, 75 MW
  • Cogent Columbus 2 · GPU colocation, Columbus
  • Cogent Columbus Office and Data Center · GPU colocation, Columbus
  • Cologix COL1 · GPU colocation, Columbus
  • Cologix COL2 · GPU colocation, Columbus
  • DartPoints CMH01 · GPU colocation, Dublin, 0.345 MW
  • Edged Edged Columbus · GPU colocation, New Albany, 24 MW
  • QTS Data Centers New Albany 1 (DC1, DC2) · GPU colocation, New Albany
  • QTS Data Centers New Albany 2 (DC1, DC2) · GPU colocation, New Albany
  • STACK Infrastructure NAL01 campus (NAL01A, NAL01B) · GPU colocation, New Albany, 60 MW
  • Vantage Data Centers OH1 (New Albany campus) · GPU colocation, New Albany, 192 MW

Colocation from our GPU colocation list; mining sites from the miner AI conversion tracker.

2. Licking CountyPJM

Site score 60 of 100

Transmission
18/25
Generation pipeline
12/20
Industrial power price
15/20
Existing and retiring plants
0/15
Sales tax exemption
4/10
Data center activity
10/10
Market
PJM
Queue (active)
1.8 GW
Agreement signed
308 MW
Planned plants (EIA)
350 MW
Top substation
345 kV
Substations 230 kV+
3
Operating plants
3 MW
Retired or retiring
0 MW
Industrial power, OH
10.3¢/kWh
Sales tax exemption
Paused

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Centerburg 138 kVPJM AI2-088, in service 2025-12Centerburg 138 kV413SolarIn study
Flint GridPJM AF1-062, in service 2026-11Jug Street 138 kV200StorageAgreement signed
Jug Street 138 kVPJM AI2-226, in service 2022-08Jug Street 138 kV200StorageIn study
Centerburg 138kVPJM AD2-067, in service 2029-04Centerburg 138kV150SolarSuspended
Centerburg 138 kVPJM AG1-034, in service 2023-10Centerburg 138 kV128SolarIn study
Hazelton - Kirk 138 kVPJM AH1-550, in service 2025-12Hazelton - Kirk 138 kV110SolarIn study
Hazelton - Kirk 138 kVPJM AI2-427, in service 2027-12Hazelton - Kirk 138 kV110SolarIn study
Union Ridge SolarPJM AF2-122, in service 2025-12Kirk 138 kV108SolarAgreement signed

Substations, 115 kV and up

  • KIRK · 8 lines345 kV
  • Unnamed · 3 lines345 kV
  • JUG STREET · 3 lines345 kV
  • Unnamed · 4 lines138 kV
  • Unnamed · 4 lines138 kV
  • Unnamed · 3 lines138 kV
  • Unnamed · 3 lines138 kV
  • WEST HEBRON · 2 lines138 kV

Planned, retiring and retired plants

  • Harvey Solar · Solar, planned 2028350 MW

Data centers, AI campuses and mining sites

  • AWS New Albany campus · AI campus, operating · DCD
  • Google New Albany · AI campus, operating · AP via ABC News
  • Meta Prometheus (New Albany campus) · AI campus, operating, 1 GW · Meta Engineering
  • Cologix COL7 (Johnstown campus) · GPU colocation, Johnstown, 36 MW, liquid cooling
  • Cologix COL8 (Johnstown campus) · GPU colocation, Johnstown, 21 MW, liquid cooling

Colocation from our GPU colocation list; mining sites from the miner AI conversion tracker.

3. Trumbull CountyPJM

Site score 58 of 100

Transmission
14/25
Generation pipeline
12/20
Industrial power price
15/20
Existing and retiring plants
9/15
Sales tax exemption
4/10
Data center activity
4/10
Market
PJM
Queue (active)
1.1 GW
Agreement signed
940 MW
Planned plants (EIA)
0 MW
Top substation
345 kV
Substations 230 kV+
1
Operating plants
2 GW
Retired or retiring
2 MW
Industrial power, OH
10.3¢/kWh
Sales tax exemption
Paused

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Trumbull Energy CenterPJM AB1-105, in service 2025-08Highland-Hanna 345kV940GasAgreement signed
Trumbull 345 kVPJM AJ1-023, in service 2024-12Trumbull 345 kV70GasIn study
Trumbull138 kVPJM AH2-239, in service 2027-03Trumbull138 kV49Solar or wind + storageIn study
Dilworth 69 kVPJM AG2-251, in service 2023-01Dilworth 69 kV29SolarIn study
Dilworth 69 kV IIPJM AG2-252, in service 2023-01Dilworth 69 kV II20SolarIn study
Dilworth 69 kV IIIPJM AG2-253, in service 2023-01Dilworth 69 kV III20SolarIn study

Substations, 115 kV and up

  • HIGHLAND · 11 lines345 kV
  • NILES POWER PLANT · 9 lines138 kV
  • HIGHLAND · 6 lines138 kV
  • NILES POWER PLANT · 5 lines138 kV
  • MASURY · 5 lines138 kV
  • Unnamed · 3 lines138 kV
  • NEWTON FALLS · 2 lines138 kV

Data centers, AI campuses and mining sites

  • Stargate Lordstown (former Foxconn plant) · AI campus, under construction · OpenAI

Colocation from our GPU colocation list; mining sites from the miner AI conversion tracker.

4. Wood CountyPJM

Site score 56 of 100

Transmission
18/25
Generation pipeline
8/20
Industrial power price
15/20
Existing and retiring plants
7/15
Sales tax exemption
4/10
Data center activity
4/10
Market
PJM
Queue (active)
1.2 GW
Agreement signed
50 MW
Planned plants (EIA)
50 MW
Top substation
345 kV
Substations 230 kV+
3
Operating plants
915 MW
Retired or retiring
7 MW
Industrial power, OH
10.3¢/kWh
Sales tax exemption
Paused

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Fostoria - Lemoyne 345 kVPJM AG2-470, in service 2025-12Fostoria - Lemoyne 345 kV300SolarIn study
Fostoria Central - Lemoyn 345 kVPJM AI2-164, in service 2025-12Fostoria Central - Lemoyn 345 kV300SolarIn study
Lemoyne 345kVPJM AH1-565, in service 2025-06Lemoyne 345kV250StorageIn study
Pemberville - West End Fostoria 69 kVPJM AH2-068, in service 2027-12Pemberville - West End Fostoria 69 kV100SolarIn study
Dowling 138 kVPJM AG2-195, in service 2024-12Dowling 138 kV53SolarIn study
Juliet EnergyPJM AF1-064, in service 2025-11Weston 69 kV50SolarAgreement signed
Fostoria - Lemoyne 138 kVPJM AH2-408, in service 2025-06Fostoria - Lemoyne 138 kV50Solar or wind + storageIn study
Fostoria - Lemoyne 138 kV IIPJM AH2-409, in service 2025-06Fostoria - Lemoyne 138 kV II30Solar or wind + storageIn study

Substations, 115 kV and up

  • LEMOYNE · 11 lines345 kV
  • Unnamed · 4 lines345 kV
  • TROY ENERGY LLC · 1 lines345 kV
  • Unnamed · 6 lines138 kV
  • Unnamed · 5 lines138 kV
  • MACLEAN · 4 lines138 kV
  • Unnamed · 3 lines138 kV
  • Unnamed · 3 lines138 kV

Planned, retiring and retired plants

  • Juliet Energy Project, LLC · Solar, planned 202650 MW

Data centers, AI campuses and mining sites

  • Meta Bowling Green · AI campus, under construction · JobsOhio

Colocation from our GPU colocation list; mining sites from the miner AI conversion tracker.

5. Jefferson CountyPJM

Site score 55 of 100

Transmission
18/25
Generation pipeline
3/20
Industrial power price
15/20
Existing and retiring plants
15/15
Sales tax exemption
4/10
Data center activity
0/10
Market
PJM
Queue (active)
199 MW
Agreement signed
0 MW
Planned plants (EIA)
63 MW
Top substation
345 kV
Substations 230 kV+
3
Operating plants
1.9 GW
Retired or retiring
2.4 GW
Industrial power, OH
10.3¢/kWh
Sales tax exemption
Paused

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Tidd 138 kVPJM AH2-126, in service 2026-10Tidd 138 kV100StorageIn study
Steubenville SolarPJM AD2-014, in service 2027-12Steubenville 69 kV50SolarSuspended
Steubenville 69 kVPJM AI2-072, in service 2024-05Steubenville 69 kV50SolarIn study

Substations, 115 kV and up

  • TIDD · 14 lines345 kV
  • FIRSTENERGY W H SAMMIS · 10 lines345 kV
  • FIRSTENERGY TORONTO · 6 lines345 kV
  • EAST AMSTERDAM · 4 lines138 kV
  • Unnamed · 3 lines138 kV
  • BROADACRE · 2 lines138 kV

Planned, retiring and retired plants

  • W H Sammis · Coal, retired 20231.7 GW
  • Cardinal · Coal, retiring 2028650 MW
  • Steubenville Solar · Solar, planned 202743 MW
  • Pike Island Hydroelectric Project · Hydro, planned 202920 MW

6. Union CountyPJM

Site score 54 of 100

Transmission
17/25
Generation pipeline
13/20
Industrial power price
15/20
Existing and retiring plants
5/15
Sales tax exemption
4/10
Data center activity
0/10
Market
PJM
Queue (active)
2.5 GW
Agreement signed
240 MW
Planned plants (EIA)
50 MW
Top substation
765 kV
Substations 230 kV+
1
Operating plants
565 MW
Retired or retiring
0 MW
Industrial power, OH
10.3¢/kWh
Sales tax exemption
Paused

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Marysville-Tangy 345 kVPJM AG1-218, in service 2024-03Marysville-Tangy 345 kV250SolarIn study
Blue Jacket-Kirby 138 kVPJM AE1-092 - moved to TC1, in service 2021-12Blue Jacket-Kirby 138 kV230SolarIn study
Marysville 345kVPJM AI2-139, in service 2023-12Marysville 345kV225SolarIn study
Marysville 345kVPJM AI2-138, in service 2023-12Marysville 345kV175SolarIn study
Beatty - Biers Run 345 kVPJM AI2-028, in service 2026-12Beatty - Biers Run 345 kV160SolarIn study
East Lima - Marysville 345 kVPJM AH2-148, in service 2027-02East Lima - Marysville 345 kV152Solar or wind + storageIn study
Marysville – Hyatt 345 kVPJM AH1-579, in service 2028-05Marysville – Hyatt 345 kV150StorageIn study
Eagle Road 138 kVPJM AH2-273, in service 2026-12Eagle Road 138 kV150SolarIn study

Substations, 115 kV and up

  • MARYSVILLE · 7 lines765 kV
  • Unnamed · 3 lines138 kV

Planned, retiring and retired plants

  • Richwood Solar and Storage · Storage, planned 202850 MW

Data center tax exemption in Ohio

Ohio data center sales and use tax exemption (ORC 122.175), granted by the Tax Credit Authority

The Tax Credit Authority may grant a full or partial sales and use tax exemption on computer data center equipment (including cooling and electrical equipment and building materials sold to contractors) for projects investing at least $100 million at the site (within 3 years for projects beginning in 2015 or later) and paying at least $1.5 million in annual Ohio payroll, with the percentage and term set by agreement; the governor directed the Authority to stop considering new requests after its June 1, 2026 meeting, while existing agreements continue.

Recent change: 2025: the HB 96 budget eliminated the exemption for construction materials, but Gov. DeWine vetoed that provision; no override was reported as of the latest coverage found (House leaders delayed an override vote in March 2026). May 27, 2026: DeWine directed the Tax Credit Authority to pause new data center exemption requests while a legislative committee studies data centers; HB 957 and SB 374 (2026) would bar new exemptions.

Source: Ohio Legislative Service Commission, effective 2025-09-30. General information, not tax advice; ask your tax advisor.

Large-load requests in PJM

PJM forecasts its summer peak at 222,106 MW in 2036, up 65,733 MW in ten years, with large load adjustments for data center growth in 14 transmission zones, including Dominion (Virginia), AEP, ComEd and PECO. Near-term adjustments now require firm commitments, so they came down from the 2025 forecast. PJM, Jan 14, 2026

AI data centers being built in Ohio

CampusDeveloperCountyMWStatusSource
PORTS-Pike Technology CampusUsers: OpenAISB Energy (SoftBank)Pike County8,000announcedGrid + on-site powerOpenAIAug 17, 2026
Meta Prometheus (New Albany campus)Users: MetaMetaLicking County1,000operatingGrid + on-site powerMeta EngineeringSep 29, 2025
Bitdeer ClaringtonBitdeerMonroe County570announcedSECMar 16, 2026
AWS New Albany campusAmazon Web ServicesLicking County-operatingDCDDec 2024
Google Columbus (South High Street)Users: GoogleGoogleFranklin County-operatingAP via ABC NewsJun 2024
Google LancasterUsers: GoogleGoogleFairfield County-operatingAP via ABC NewsJun 2024
Google New AlbanyUsers: GoogleGoogleLicking County-operatingAP via ABC NewsJun 2024
Meta Bowling GreenUsers: MetaMetaWood County-under constructionJobsOhioApr 9, 2025
Stargate Lordstown (former Foxconn plant)Users: OpenAISoftBank / FoxconnTrumbull County-under constructionOpenAISep 23, 2025

Busiest points of interconnection in Ohio

#Point of interconnectionCountyISORequestsQueued MWMostly
1Marysville-Flatlick 765 kVMadison County, OHPJM115,200Solar
2Marysville - Sorenson 765 kVLogan County, OHPJM71,955Solar

How the score works

Six parts out of 100: transmission (25), generation in the queue (20), the state's industrial power price (20), existing and retiring plants (15), sales tax exemption (10) and data center activity (10). The site finder's methodology prints each formula and every source with its date. Markets: PJM (Mid-Atlantic and Midwest).

All states

Discuss a transaction

Funding a data center or the GPUs going into one in Ohio? Tell us about the site and the capital you need, and we will come back with the lenders and the structure that fit. Operators raising debt for a cluster can start at gpulenders.com.