49 South Dakota counties scored on transmission, the interconnection queue, power price and tax. Updated October 18, 2026.

Open a county for its queue requests, substations, plants and data centers.

CountyScorePipelinePower price
46980 MW9.5¢/kWh
43500 MW9.5¢/kWh
41-9.5¢/kWh
41100 MW9.5¢/kWh
401.3 GW9.5¢/kWh
40408 MW9.5¢/kWh
40240 MW9.5¢/kWh
37-9.5¢/kWh
35300 MW9.5¢/kWh
35-9.5¢/kWh
32-9.5¢/kWh
30-9.5¢/kWh
30-9.5¢/kWh
30-9.5¢/kWh
29120 MW9.5¢/kWh
29-9.5¢/kWh
2999 MW9.5¢/kWh
28-9.5¢/kWh
27-9.5¢/kWh
26300 MW9.5¢/kWh
26-9.5¢/kWh
26-9.5¢/kWh
26-9.5¢/kWh
26-9.5¢/kWh
26-9.5¢/kWh
26-9.5¢/kWh
26-9.5¢/kWh
23270 MW9.5¢/kWh
23200 MW9.5¢/kWh
23-9.5¢/kWh
2299 MW9.5¢/kWh
22-9.5¢/kWh
21400 MW9.5¢/kWh
21-9.5¢/kWh
21-9.5¢/kWh
20162 MW9.5¢/kWh
20-9.5¢/kWh
20-9.5¢/kWh
20-9.5¢/kWh
20-9.5¢/kWh
20-9.5¢/kWh
20-9.5¢/kWh
19-9.5¢/kWh
19-9.5¢/kWh
19-9.5¢/kWh
19-9.5¢/kWh
188 MW9.5¢/kWh
17-9.5¢/kWh
17-9.5¢/kWh

Pipeline: active generation and storage requests in the ISO queue, or EIA planned plants where larger (outside the ISOs). Top kV: highest substation voltage. Power price: the state's industrial average. DCs: GPU colocation, mining sites and AI campuses.

What the data shows

The strongest South Dakota counties for a large AI load are Brookings County (46), Grant County (43) and Minnehaha County (41) on the site score. South Dakota sits in SPP, MISO and utility territory; its ISO queues hold 5.4 GW of active generation and storage requests, 927 MW of them with a signed interconnection agreement, and it has 9 substations at 345 kV and up.

Industrial power averaged 9.5¢/kWh (EIA, July 2026 YTD), against 8.7¢/kWh a year earlier, the 31st lowest of the 50 states and DC. South Dakota has no data center-specific sales tax exemption. We track 0 AI campuses and 2 GPU-ready colocation facilities here.

Top 6 counties in detail

1. Brookings CountySPP

Site score 46 of 100

Transmission
18/25
Generation pipeline
7/20
Industrial power price
16/20
Existing and retiring plants
5/15
Sales tax exemption
0/10
Data center activity
0/10
Market
SPP
Queue (active)
980 MW
Agreement signed
0 MW
Planned plants (EIA)
5 MW
Top substation
345 kV
Substations 230 kV+
3
Operating plants
682 MW
Retired or retiring
0 MW
Industrial power, SD
9.5¢/kWh
Sales tax exemption
None

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Split Rock - White (WAPA) 345.0kVMISO J3964, in service 2030-01Split Rock - White (WAPA) 345.0kV490SolarIn study
BROOKINGS COUNTYMISO J3963, in service 2030-01BROOKINGS COUNTY490SolarIn study

Substations, 115 kV and up

  • BROOKINGS COUNTY · 7 lines345 kV
  • WHITE · 7 lines345 kV
  • DEER CREEK STATION · 1 lines345 kV
  • Unnamed · 6 lines115 kV
  • Unnamed · 3 lines115 kV
  • Unnamed · 3 lines115 kV
  • Unnamed · 3 lines115 kV
  • Unnamed · 3 lines115 kV

2. Grant CountyMISO

Site score 43 of 100

Transmission
16/25
Generation pipeline
5/20
Industrial power price
16/20
Existing and retiring plants
6/15
Sales tax exemption
0/10
Data center activity
0/10
Market
MISO
Queue (active)
500 MW
Agreement signed
0 MW
Planned plants (EIA)
0 MW
Top substation
345 kV
Substations 230 kV+
2
Operating plants
915 MW
Retired or retiring
0 MW
Industrial power, SD
9.5¢/kWh
Sales tax exemption
None

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Big Stone South 345 kV substationMISO J4153, in service 2031-06Big Stone South 345 kV substation250StorageIn study
Big Stone South 345 kV substationMISO J4081, in service 2031-06Big Stone South 345 kV substation250StorageIn study

Substations, 115 kV and up

  • BIG STONE SOUTH · 5 lines345 kV
  • BIG STONE · 6 lines230 kV

3. Minnehaha CountyMISO

Site score 41 of 100

Transmission
16/25
Generation pipeline
0/20
Industrial power price
16/20
Existing and retiring plants
7/15
Sales tax exemption
0/10
Data center activity
2/10
Market
MISO
Queue (active)
0 MW
Agreement signed
0 MW
Planned plants (EIA)
0 MW
Top substation
345 kV
Substations 230 kV+
2
Operating plants
406 MW
Retired or retiring
166 MW
Industrial power, SD
9.5¢/kWh
Sales tax exemption
None

Substations, 115 kV and up

  • SPLIT ROCK · 12 lines345 kV
  • SIOUX FALLS · 11 lines230 kV
  • LAWRENCE · 4 lines115 kV
  • Unnamed · 4 lines115 kV
  • Unnamed · 4 lines115 kV
  • Unnamed · 3 lines115 kV
  • Unnamed · 3 lines115 kV
  • Unnamed · 3 lines115 kV

Planned, retiring and retired plants

  • Angus Anson · Gas, retiring 2029166 MW

Data centers, AI campuses and mining sites

  • TierPoint Sioux Falls East · GPU colocation, Sioux Falls
  • TierPoint Sioux Falls West · GPU colocation, Sioux Falls

Colocation from our GPU colocation list; mining sites from the miner AI conversion tracker.

4. Pennington CountyUtility: WAPA Rocky Mountain

Site score 41 of 100

Transmission
16/25
Generation pipeline
4/20
Industrial power price
16/20
Existing and retiring plants
5/15
Sales tax exemption
0/10
Data center activity
0/10
Market
Utility: WAPA Rocky Mountain
Queue (active)
0 MW
Agreement signed
0 MW
Planned plants (EIA)
100 MW
Top substation
230 kV
Substations 230 kV+
4
Operating plants
278 MW
Retired or retiring
108 MW
Industrial power, SD
9.5¢/kWh
Sales tax exemption
None

Substations, 115 kV and up

  • NEW UNDERWOOD · 7 lines230 kV
  • SOUTH RAPID CITY · 3 lines230 kV
  • RAPID CITY DC TIE · 2 lines230 kV
  • LANGE · 2 lines230 kV
  • Unnamed · 3 lines115 kV

Planned, retiring and retired plants

  • Ben French · Gas, retiring 2027108 MW
  • Lange Generating Station · Gas, planned 2026100 MW

5. Deuel CountyMISO

Site score 40 of 100

Transmission
10/25
Generation pipeline
8/20
Industrial power price
16/20
Existing and retiring plants
6/15
Sales tax exemption
0/10
Data center activity
0/10
Market
MISO
Queue (active)
1.3 GW
Agreement signed
0 MW
Planned plants (EIA)
145 MW
Top substation
230 kV
Substations 230 kV+
1
Operating plants
803 MW
Retired or retiring
0 MW
Industrial power, SD
9.5¢/kWh
Sales tax exemption
None

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Astoria 345kV substationMISO J3941, in service 2030-05Astoria 345kV substation1,144GasIn study
Astoria 345kV substationMISO J3400, in service 2028-04Astoria 345kV substation142Solar or wind + storageIn study

Substations, 115 kV and up

  • BLAIR · 3 lines230 kV

Planned, retiring and retired plants

  • Toronto Power Plant · Gas, planned 2029145 MW

6. Brown CountySPP

Site score 40 of 100

Transmission
14/25
Generation pipeline
6/20
Industrial power price
16/20
Existing and retiring plants
4/15
Sales tax exemption
0/10
Data center activity
0/10
Market
SPP
Queue (active)
408 MW
Agreement signed
138 MW
Planned plants (EIA)
32 MW
Top substation
345 kV
Substations 230 kV+
1
Operating plants
327 MW
Retired or retiring
0 MW
Industrial power, SD
9.5¢/kWh
Sales tax exemption
None

Largest queue requests

ProjectPoint of interconnectionMWTypeStage
Groton 345 kV SubstationSPP GEN-2024-035, in service 2027-09Groton 345 kV Substation270Solar or wind + storageIn study
Siebrecht 115 kV SubstationSPP ERAS-2025-035, in service 2029-06Siebrecht 115 kV Substation138GasAgreement signed

Substations, 115 kV and up

  • GROTON · 7 lines345 kV
  • Unnamed · 3 lines115 kV
  • ABERDEEN · 3 lines115 kV
  • Unnamed · 3 lines115 kV
  • GROTON · 2 lines115 kV

Planned, retiring and retired plants

  • Aberdeen CT · Gas, planned 202632 MW

Data center tax exemption in South Dakota

No data center-specific sales tax exemption found. Bills to create one (including HB 1005 in 2026) failed in the 2025 and 2026 sessions.

Recent change: 2026 proposals for a data center sales tax exemption failed; SB 135 (Data Center Bill of Rights) passed after language banning future data center tax exemptions was removed.

Source: KTIV, 2026-03-10. General information, not tax advice; ask your tax advisor.

Busiest points of interconnection in South Dakota

#Point of interconnectionCountyISORequestsQueued MWMostly
1Astoria 345kV substationDeuel County, SDMISO21,286Gas

How the score works

Six parts out of 100: transmission (25), generation in the queue (20), the state's industrial power price (20), existing and retiring plants (15), sales tax exemption (10) and data center activity (10). The site finder's methodology prints each formula and every source with its date. Markets: SPP (Plains), MISO (Midwest and South), Utility territory (no ISO/RTO).

All states