Offtake Contract Due Diligence

What to check before you fund.

What it covers

The offtake contract is the repayment source on most GPU loans, and the clauses that decide it are delivery dates, cure periods, termination and security. In many contracts a missed deployment date lets the customer walk and recover prepaid fees.

What you should check for

RevenueTake-or-pay amount and termCommitted spend, term and start date, and whether the commitment survives a delivery slip.
Payment securityPrepayment, deposit, letter of credit, guarantee or escrow. IREN's Microsoft contract requires 20% of each tranche up front.
Debt service follows deliveryPayments start when the cluster bills, with interest-only until then.
Delivery and performanceReady-for-service dateA date the hardware allocation and the colo's power date can both meet, with the acceptance test defined.
Cure periodLong enough to replace a failed delivery or move the cluster; 30-45 days is typical.
SLA creditsCredit levels and caps, and whether repeated misses become a termination right.
ExitNo termination for conveniencePlus credit support: SharonAI's $1.25B contract with ESDS has both, including $140M in letters of credit.
Assignment to the lenderCollateral assignment of the contract and consent to step in, so the revenue can follow the cluster to a backup operator.

Sources: GPU Lenders (American Compute), American Compute.

What the contract has to carry

An offtake agreement is the customer contract that buys the cluster's compute for a fixed term, often take-or-pay. Many give the provider a 30-45 day cure period for a missed deployment date, after which the customer may terminate and recover prepaid fees. Larger Blackwell orders wait 6-9 months for hardware, so the cure period and the lead time have to fit together.

Uptime commitments sit in the same contract. Compare the uptime, power and delivery dates it promises with the site's design and the hardware schedule. What the clauses mean legally is for your counsel.

Red flags

LOI at fundingA letter of intent is not revenue. Some offtakers walk at the last minute.
Capacity cuts on requestRequests to defer delivery, cut reserved capacity or move to on-demand are early default signals. Microsoft dropped a couple hundred MW of leases in February 2025 (TD Cowen).
Cure period shorter than lead timeIf replacement hardware takes 6-9 months and the cure is 30 days, one delivery problem can end the contract.

Where GPU Deals Break

The 52-slide deck: where GPU loans and leases break, from the order to the site to the lease, one diagram per risk.

Book a call

Send us the equipment list and the loan or lease you have in mind. We will come back with a proposed scope and the questions we would need answered.

San Francisco1160 Battery Street EastSuite 100San Francisco, CA 94111
New York430 Park AvenueNew York, NY 10022

Prefer email? hello@amcompute.com