Every GPU financing with a public credit rating.

What it shows

16 rated financings, $67.9B. 8 are rated investment grade, all since Oct 16, 2025.

The rating follows the customer, not the borrower. CoreWeave is rated Ba3 by Moody’s; its DDTL 4.0, secured on GPUs and a six-year Meta contract in a bankruptcy-remote subsidiary, is rated A3.

Investment grade prices at SOFR + 2.25% to 3%, BB at 4.5% to 5.5%. CoreWeave’s unsecured notes pay 9%.

Every rated financing

Newest first. Updated October 10, 2026.

DateFinancingSizeRatingPricingBacked byCustomerSource
Oct 1, 2026Lambda fixed-rate DDTL$1.01BDBRS A (low), Moody's Baa16.78% fixedGPUs + customer contractTwo investment-grade offtakers (unnamed); GB300 and Vera Rubin GPUs in Seattle, Kansas City and DallasMorningstar DBRS
Aug 27, 2026Lambda Term Loan B$926MMoody's Baa2SOFR + 3.00% (OID 99.5)GPUs + customer contractNVIDIA (take-or-pay, single site in Quebec)Moody's Ratings
Aug 27, 2026Nscale Ward County DDTL$1.85BMoody's Baa1Term SOFR + 2.375% (fixed tranche: swap rate + 2.375%)GPUs + customer contractHyperscaler rated Aa3 or better (six-year take-or-pay; Nscale's S-1 files a Microsoft statement of work)Moody's Ratings
Aug 7, 2026CoreWeave DDTL 5.5$2.6BMoody's Ba2, Fitch BB+SOFR + 5.50%GPUs + customer contractAI, financial services and technology customers; contracts average about 3 years against a 5-year loanSEC EDGAR
Jun 15, 2026Cipher Stingray notes$810MMoody's Ba2, Fitch BB-6.0% fixedAI data center leaseAmazon Web Services (70 MW IT, Texas), per press reportsSEC EDGAR
Jun 9, 2026Hut 8 Beacon Point notes$4.25BMoody's Baa26.129% fixedAI data center leaseUndisclosed investment-grade tenant (15-year triple-net lease, 352 MW, Texas)SEC EDGAR
May 29, 2026IREN Microsoft GPU financing$3.65BFitch A, DBRS A (low)SOFR + 2.25% (DDTL); USPP 5.96% fixed (~SOFR + 2.13% equivalent per IREN)GPUs + customer contractMicrosoft (about $9.7B, five-year GPU services contract, GB300 at Childress, Texas)SEC EDGAR
May 15, 2026CoreWeave DDTL 5.0$3.1BMoody's Ba2, Fitch BB+SOFR + 4.50%GPUs + customer contractTwo large non-investment-grade customers (unnamed)SEC EDGAR
Apr 27, 2026Hut 8 River Bend notes$3.25BS&P BBB-, Fitch BBB-6.192% fixedAI data center leaseFluidstack (15-year lease, 245 MW, Louisiana), rent backstopped by GoogleSEC EDGAR
Mar 30, 2026CoreWeave DDTL 4.0$8.5BMoody's A3, DBRS A (low)SOFR + 2.25% (floating); UST + 2.00% (fixed, ~5.9%)GPUs + customer contractMeta (six-year take-or-pay; Meta rated Aa3)Moody's Ratings
Feb 11, 2026Cipher Black Pearl notes$2BMoody's Ba2, Fitch BB-6.125% fixedAI data center leaseAmazon Web Services (15-year lease, 216 MW IT, Texas), rent guaranteed by Amazon.comSEC EDGAR
Nov 13, 2025Cipher Barber Lake notes$1.73BMoody's Ba3, Fitch BB-7.125% fixedAI data center leaseFluidstack (Barber Lake, Texas), rent backstopped by GoogleSEC EDGAR
Oct 22, 2025WULF Compute notes$3.2BMoody's Ba2, S&P BB, Fitch BB7.75% fixedAI data center leaseFluidstack (Lake Mariner, New York), rent backstopped by GoogleSEC EDGAR
Oct 16, 2025Meta Hyperion (Beignet) notes$27.3BS&P A+6.581% fixedAI data center leaseMeta (lease of the Hyperion AI campus, Louisiana, with a Meta residual value guarantee)S&P Global Ratings
Jul 25, 2025CoreWeave 9.00% notes due 2031$1.75BS&P B9.0% fixedCorporateNone (corporate debt)S&P Global Ratings (via AlacraStore)
May 27, 2025CoreWeave 9.25% notes due 2030$2BS&P B9.25% fixedCorporateNone (corporate debt)S&P Global Ratings (via AlacraStore)