B300 and GB300 NVL72 Power and Cooling Requirements

Whether the site can keep the equipment running.

What it covers

NVIDIA rates a DGX B300 at 14.5 kW (15 kW maximum), air-cooled. NVIDIA does not publish a rack figure for the GB300 NVL72, which it describes as fully liquid-cooled; OEMs rate the rack at about 135-140 kW, with peaks up to 155 kW. Most data centers run 10-30 kW per rack, so the site is usually the constraint.

What you should check for

Before signingCommitted kW per rackAbout 15 kW per DGX B300, and the OEM's peak figure for a GB300 NVL72 rack (140-155 kW), in the signed order.
Cooling type for the exact SKUAir-cooled DGX or HGX B300, liquid-cooled HGX B300, or NVL72: each has different site needs.
Liquid loop specifiedCoolant distribution units, manifolds, facility water at the temperature the racks need, and who maintains them.
Before deliveryFloor and weightA DGX B300 with power supplies weighs 168 kg; NVL72 racks are far heavier and need a rated floor path.
Power energizedEnergization confirmed in writing, not expected.

Sources: NVIDIA, GIGABYTE, Lenovo Press, American Compute.

Power per system

SystemPer GPUPer server or rackCooling15 kW rack30 kW rack40 kW rack80 kW rack
DGX H100 / H200700 W10.2 kW maxAir1 server2 servers3 servers4 servers
DGX B300Not published by NVIDIA14.5 kW (15 kW max)Air (DGX); OEM HGX B300 in air or liquid1 server2 servers2 servers4 servers
GB200 NVL72Not published per GPUAbout 120 kW per rackLiquidNoNoNoNo
GB300 NVL72Not published per GPUUp to 140 kW per rack (GIGABYTE)LiquidNoNoNoNo

Servers that fit a rack's power budget, capped at four 8-GPU servers. Air cooling stops working past roughly 40 kW per rack.

Sources: NVIDIA, American Compute, GIGABYTE.

B300 vs GB300

Both use the Blackwell Ultra GPU. B300 ships in 8-GPU servers (NVIDIA DGX B300 and OEM HGX B300 systems) that sit in ordinary racks, air- or liquid-cooled, at about 15 kW each. GB300 pairs the GPUs with Grace CPUs: a GB300 NVL72 is one liquid-cooled rack of 72 GPUs and 36 CPUs in a single NVLink domain, at about 135-140 kW.

For a lender the difference is the site and the exit. An 8-GPU server can go into many existing halls and trades in a market with years of history from earlier generations; resale market data for whole NVL72 racks is still limited, and only liquid-cooled sites can take them.

B300: about 15 kW per server

A DGX B300 is a 10-rack-unit system rated at 14.5 kW with a 15 kW maximum. The power supply version has twelve 3.2 kW supplies in N+N redundancy and is cooled by air at about 1,500 CFM; a busbar version takes 54 V DC from rack power shelves instead. NVIDIA does not publish a per-GPU figure for B300; industry reports put it at up to about 1,400 W, double the H100's 700 W.

Two DGX B300s fill a 30 kW rack; a typical 15 kW rack holds one. A cluster of 32 B300 servers needs 16 racks at 30 kW, or 8 at 80 kW where space and cooling allow. Liquid-cooled HGX B300 servers pack more per rack and need a coolant distribution unit, usually tied to facility water.

GB300 NVL72: up to 140 kW per rack

A GB300 NVL72 puts 72 GPUs and 36 Grace CPUs in one rack with one NVLink domain. GIGABYTE rates its rack at up to 140 kW. Lenovo's build is hybrid-cooled: cold plates fed by a coolant distribution unit on the CPUs, GPUs, NVLink switches and ConnectX-8 adapters, air for drives, optics and power distribution.

Past roughly 40 kW per rack, air cooling stops working. A GB300 site needs liquid cooling, the grid capacity, reinforced floors and plumbing in place before the racks arrive. GB200 NVL72 racks, at about 120 kW, set the same bar a year earlier, and early racks were reported to overheat while NVIDIA revised designs.

Why a lender cares

Density decides the buyer pool. Only a small set of purpose-built, liquid-cooled data centers can host the newest systems, so they are also the likely buyers in a liquidation. A site evaluation shows whether the borrower's own site is one of them.

Delay spends residual. A B300 falls from about 80% of list price to 52-64% in a year in our conservative case; a cluster waiting on power spends that year before earning anything.

Red flags

Two B300 servers in a 20 kW cabinet2 x 14.5 kW is 29 kW. Either the servers run power-capped or the circuit runs over its rating.
NVL72 racks into an air-cooled hallPast about 40 kW per rack, direct-to-chip liquid cooling is mandatory.
Running new silicon at half powerVery few operators accept it, and offtake contracts with performance terms usually do not allow for it.

Where GPU Deals Break

The 52-slide deck: where GPU loans and leases break, from the order to the site to the lease, one diagram per risk.

Book a call

Send us the equipment list and the loan or lease you have in mind. We will come back with a proposed scope and the questions we would need answered.

San Francisco1160 Battery Street EastSuite 100San Francisco, CA 94111
New York430 Park AvenueNew York, NY 10022

Prefer email? hello@amcompute.com