B300 and GB300 NVL72 Power and Cooling Requirements
Whether the site can keep the equipment running.
What it covers
NVIDIA rates a DGX B300 at 14.5 kW (15 kW maximum), air-cooled. NVIDIA does not publish a rack figure for the GB300 NVL72, which it describes as fully liquid-cooled; OEMs rate the rack at about 135-140 kW, with peaks up to 155 kW. Most data centers run 10-30 kW per rack, so the site is usually the constraint.
What you should check for
| Before signing | Committed kW per rack | About 15 kW per DGX B300, and the OEM's peak figure for a GB300 NVL72 rack (140-155 kW), in the signed order. |
| Cooling type for the exact SKU | Air-cooled DGX or HGX B300, liquid-cooled HGX B300, or NVL72: each has different site needs. | |
| Liquid loop specified | Coolant distribution units, manifolds, facility water at the temperature the racks need, and who maintains them. | |
| Before delivery | Floor and weight | A DGX B300 with power supplies weighs 168 kg; NVL72 racks are far heavier and need a rated floor path. |
| Power energized | Energization confirmed in writing, not expected. |
Sources: NVIDIA, GIGABYTE, Lenovo Press, American Compute.
Power per system
| System | Per GPU | Per server or rack | Cooling | 15 kW rack | 30 kW rack | 40 kW rack | 80 kW rack |
|---|---|---|---|---|---|---|---|
| DGX H100 / H200 | 700 W | 10.2 kW max | Air | 1 server | 2 servers | 3 servers | 4 servers |
| DGX B300 | Not published by NVIDIA | 14.5 kW (15 kW max) | Air (DGX); OEM HGX B300 in air or liquid | 1 server | 2 servers | 2 servers | 4 servers |
| GB200 NVL72 | Not published per GPU | About 120 kW per rack | Liquid | No | No | No | No |
| GB300 NVL72 | Not published per GPU | Up to 140 kW per rack (GIGABYTE) | Liquid | No | No | No | No |
Servers that fit a rack's power budget, capped at four 8-GPU servers. Air cooling stops working past roughly 40 kW per rack.
Sources: NVIDIA, American Compute, GIGABYTE.
B300 vs GB300
Both use the Blackwell Ultra GPU. B300 ships in 8-GPU servers (NVIDIA DGX B300 and OEM HGX B300 systems) that sit in ordinary racks, air- or liquid-cooled, at about 15 kW each. GB300 pairs the GPUs with Grace CPUs: a GB300 NVL72 is one liquid-cooled rack of 72 GPUs and 36 CPUs in a single NVLink domain, at about 135-140 kW.
For a lender the difference is the site and the exit. An 8-GPU server can go into many existing halls and trades in a market with years of history from earlier generations; resale market data for whole NVL72 racks is still limited, and only liquid-cooled sites can take them.
B300: about 15 kW per server
A DGX B300 is a 10-rack-unit system rated at 14.5 kW with a 15 kW maximum. The power supply version has twelve 3.2 kW supplies in N+N redundancy and is cooled by air at about 1,500 CFM; a busbar version takes 54 V DC from rack power shelves instead. NVIDIA does not publish a per-GPU figure for B300; industry reports put it at up to about 1,400 W, double the H100's 700 W.
Two DGX B300s fill a 30 kW rack; a typical 15 kW rack holds one. A cluster of 32 B300 servers needs 16 racks at 30 kW, or 8 at 80 kW where space and cooling allow. Liquid-cooled HGX B300 servers pack more per rack and need a coolant distribution unit, usually tied to facility water.
GB300 NVL72: up to 140 kW per rack
A GB300 NVL72 puts 72 GPUs and 36 Grace CPUs in one rack with one NVLink domain. GIGABYTE rates its rack at up to 140 kW. Lenovo's build is hybrid-cooled: cold plates fed by a coolant distribution unit on the CPUs, GPUs, NVLink switches and ConnectX-8 adapters, air for drives, optics and power distribution.
Past roughly 40 kW per rack, air cooling stops working. A GB300 site needs liquid cooling, the grid capacity, reinforced floors and plumbing in place before the racks arrive. GB200 NVL72 racks, at about 120 kW, set the same bar a year earlier, and early racks were reported to overheat while NVIDIA revised designs.
Why a lender cares
Density decides the buyer pool. Only a small set of purpose-built, liquid-cooled data centers can host the newest systems, so they are also the likely buyers in a liquidation. A site evaluation shows whether the borrower's own site is one of them.
Delay spends residual. A B300 falls from about 80% of list price to 52-64% in a year in our conservative case; a cluster waiting on power spends that year before earning anything.
Red flags
| Two B300 servers in a 20 kW cabinet | 2 x 14.5 kW is 29 kW. Either the servers run power-capped or the circuit runs over its rating. |
| NVL72 racks into an air-cooled hall | Past about 40 kW per rack, direct-to-chip liquid cooling is mandatory. |
| Running new silicon at half power | Very few operators accept it, and offtake contracts with performance terms usually do not allow for it. |
Where GPU Deals Break
The 52-slide deck: where GPU loans and leases break, from the order to the site to the lease, one diagram per risk.
Book a call
Send us the equipment list and the loan or lease you have in mind. We will come back with a proposed scope and the questions we would need answered.
Prefer email? hello@amcompute.com