B300 and GB300 NVL72 Power and Cooling Requirements
Whether the site can keep the equipment running.
What it covers
NVIDIA rates a DGX B300 at 14.5 kW, air-cooled, and OEMs rate a GB300 NVL72 rack at up to 140 kW with liquid cooling. Most data centers run 10-30 kW per rack, so the site decides whether the cluster can be delivered, run and resold.
What you should check for
| Before signing | Committed kW per rack | At least 15 kW per B300 server or 140 kW per GB300 NVL72 rack, in the signed order. |
| Cooling type for the exact SKU | Air-cooled DGX or HGX B300, liquid-cooled HGX B300, or NVL72: each has different site needs. | |
| Liquid loop specified | Coolant distribution units, manifolds and facility water in the design, with who maintains them. | |
| Before delivery | Floor and weight | A DGX B300 with power supplies weighs 168 kg; NVL72 racks are far heavier and need a rated floor path. |
| Power energized | Energization confirmed in writing, not expected. |
Sources: NVIDIA, GIGABYTE, Lenovo Press, American Compute.
Power per system
| System | Per GPU | Per server or rack | Cooling | 15 kW rack | 30 kW rack | 40 kW rack | 80 kW rack |
|---|---|---|---|---|---|---|---|
| DGX H100 / H200 | 700 W | 10.2 kW max | Air | 1 server | 2 servers | 3 servers | 4 servers |
| DGX B300 | 1,400 W (our report) | 14.5 kW | Air (DGX); liquid HGX variants | 1 server | 2 servers | 2 servers | 4 servers |
| GB200 NVL72 | Not published per GPU | About 120 kW per rack | Liquid only | No | No | No | No |
| GB300 NVL72 | Not published per GPU | Up to 140 kW per rack (GIGABYTE) | Liquid (about 90% of heat), air for drives and optics | No | No | No | No |
Servers that fit a rack's power budget, capped at four 8-GPU servers. Air cooling stops working past roughly 40 kW per rack.
Sources: NVIDIA, American Compute, GIGABYTE.
B300: about 15 kW per server
A DGX B300 is a 10-rack-unit system drawing 14.5 kW, with twelve 3.2 kW power supplies, cooled by air at about 1,500 CFM. Our residual report puts the B300 GPU at 1,400 W, double the H100's 700 W.
Two DGX B300s fill a 30 kW rack; a typical 15 kW rack holds one. A cluster of 32 B300 servers needs 16 racks at 30 kW, against 8 at 80 kW. Liquid-cooled HGX B300 variants pack more servers per rack and require a facility water loop.
GB300 NVL72: up to 140 kW per rack
A GB300 NVL72 puts 72 GPUs and 36 Grace CPUs in one rack with one NVLink domain. GIGABYTE rates its rack at up to 140 kW. Lenovo's build is hybrid-cooled: cold plates fed by a coolant distribution unit on the CPUs, GPUs, NVLink switches and ConnectX-8 adapters, air for drives, optics and power distribution.
Past roughly 40 kW per rack, air cooling stops working. A GB300 site needs liquid cooling, the grid capacity, reinforced floors and plumbing in place before the racks arrive. GB200 NVL72 racks, at about 120 kW, set the same bar a year earlier, and early racks were reported to overheat while NVIDIA revised designs.
Why a lender cares
Density decides the buyer pool. Only a small set of purpose-built, liquid-cooled data centers can host the newest systems, so they are also the only buyers in a liquidation. An appraisal of a GB300 cluster assumes such a buyer exists; the site evaluation checks the borrower has one today.
Delay spends residual. A B300 falls from about 80% of list price to 52-64% in a year in our conservative case; a cluster waiting on power spends that year before earning anything.
Red flags
| Two B300 servers in a 20 kW cabinet | 2 x 14.5 kW is 29 kW. Either the cabinet runs throttled or the second server never powers on. |
| NVL72 racks into an air-cooled hall | Past about 40 kW per rack, direct-to-chip liquid cooling is mandatory. |
| Running new silicon at half power | Very few operators accept it, and the offtaker's performance terms will not. |
Discuss a transaction
Send us the equipment list and the loan or lease you have in mind. We will come back with an indication and the questions we would need answered.
Prefer email? hello@amcompute.com